Yadana gas field | |
---|---|
Country | Myanmar |
Region | Andaman Sea |
Location | Mottama offshore area |
Offshore/onshore | offshore |
Operator(s) | Total S.A. |
Partners | Total S.A. (31.2%) Chevron Corporation (28.3%) PTT Public Company Limited (25.5%) Myanma Oil and Gas Enterprise (15%) |
Field history | |
Discovery | 1980 |
Start of development | 1995 |
Start of production | 1998 |
Production | |
Current production of gas (billion cubic meters per year) | 8 |
Estimated gas in place (billion cubic meters) | 150 |
The Yadana gas field is an offshore gas field in the Andaman Sea. It is located about 60 kilometres (37 mi) offshore to the nearest landfall in Myanmar.[1]
Contents |
The Yadana gas field contains more than 150 billion cubic meters of natural gas and has an expected field life of over 30 years.[1] In 2009, the output averaged 780 million cubic feet per day (22×10 6 m3/d).[2]
The gas field lays around 1,300 metres (4,300 ft) beneath the seabed in the water depth around 40 metres (130 ft). The offshore production complex consist of two remote wellhead platforms, one bridge-linked wellhead platform, a production platform, a living quarters platform, and a medium compression platform. Produced gas is exported through two pipelines. The first, 409 kilometres (254 mi) long pipeline runs 346 kilometres (215 mi) underwater from Yadana to Daminseik at the coast. From there, a 63-kilometre (39 mi) onshore section runs to the Thai border. The onshore section crosses a region inhabited by the Karen, a minority ethnic group hostile to the government.[3] Construction of the pipeline was completed in 1998 and it cost US$1.2 billion.[4] This pipeline has capacity of 500 million cubic feet per day (14×10 6 m3/d).[2]
The second, 287 kilometres (178 mi) long pipeline pipeline from the Yadana to Yangon was inaugurated on 12 June 2010. The 24-inch (610 mm) pipeline has a 151 kilometres (94 mi) long offshore and 136 kilometres (85 mi) long onshore sections.[5] The pipeline has capacity of 150 million cubic feet per day (4.2×10 6 m3/d).[2]
The Yadana gas field and pipelines are operated by Total S.A., a French energy group, with Chevron Corporation, a United States-based company, as its junior partner along with PTT, a Thai state-owned oil and gas company, and Myanma Oil and Gas Enterprise (MOGE), a state-owned enterprise of Myanmar.[4][6] Operator of the gas field is Total. Total has working interest of 31.2%, Chevron 28.3%, PTT 25.5%, and MOGE 15%.
The Yadana project has been subject to much criticism in the international community, particularly because companies of democratic nations invested in a regime that has been noted for its human rights violations.[7] The State Law and Order Restoration Council came under intense scrutiny for their human rights abuses during the construction of the pipeline and their involvement in the project led to a lawsuit being filed against Unocal.[8] Evidence collected by ERI (EarthRights International) suggests that villagers are routinely forced to work in various guises. One former soldier from the 273 battalion said : "We were told it was a 30 year project and the country got half, and the foreigners got half of the benefit. We ask the villagers to carry shell ammunition, food and supplies. During the portering the soldiers treat porters not so good. I do not want to mention about these bad things so much since I myself I have done it to these people as well at that time." Troops routinely force civilians to work for them and those who refuse are often beaten, tortured or sometimes killed. Since early 2009 Burmese soldiers have ordered villagers to build a new police camp. "The Yadana project ushered in the Burmese army and the Burmese army continues to provide security for the companies and the project. The Total company has been complicit in abuses," said Matthew Smith of ERI.[9]
The 2006 documentary Total Denial depicted the controversy surrounding the construction of the Yadana pipeline.